Economic Analysis for Construction of Bridge for a Poverty Driven Rural Area in Kurigram District of Bangladesh
Mohirul Islam Mohir1,, Kazi Mostafa Arif2
1Development Planner, SPGP, JICA, NILG, Agargaon, Dhaka 1207, Bangladesh
2Department of Economics, Islamic University, Kushtia 7003, Bangladesh
Abstract | |
1. | Introduction |
2. | Objectives of the Study |
3. | Literature Review |
4. | Methodology |
5. | Selection of Study Area |
6. | Results and Discussions |
7. | Conclusions and Recommendations |
References |
Abstract
The aim of this study is to find out the suitability of bridge for a poverty driven rural area in Bangladesh in the context of social and economic aspects. The study employed Participatory Rural Appraisal (PRA) approach to capture social benefit and also applied Benefit Cost Ratio (BCR), Net Present Value (NPV) and Internal Rate of Return (IRR) assessing economic aspect. From PRA appaisal it is known that people of the Bridge areas strongly supported construction of Bridge as they perceived that the Bridge has a positive impact on socio-economic condition by changing existing communication system through construction of the proposed bridge. From the Economic Analysis, it is found that the BCR is 1.91, NPV is Tk. 17,645 Lakh and IRR is 31% which thus indicate positive returns of this proposed project. In addition, by construction of the proposed 1490m long bridge over the Teesta river, the travel distance from Chilmari Upazila of Kurigram District to Dhaka would be reduced by about 160 km. The Bridge has a social acceptance and hence it would enhance better communication that would result better economy of study area as well as the nation.
Keywords: Focus Group Discussion (FGD), Benefit Cost Ratio (BCR), Net Present Value (NPV) and Economic Internal Rate of Return (EIRR)
Copyright © 2016 Science and Education Publishing. All Rights Reserved.Cite this article:
- Mohirul Islam Mohir, Kazi Mostafa Arif. Economic Analysis for Construction of Bridge for a Poverty Driven Rural Area in Kurigram District of Bangladesh. American Journal of Rural Development. Vol. 4, No. 3, 2016, pp 71-77. https://pubs.sciepub.com/ajrd/4/3/3
- Mohir, Mohirul Islam, and Kazi Mostafa Arif. "Economic Analysis for Construction of Bridge for a Poverty Driven Rural Area in Kurigram District of Bangladesh." American Journal of Rural Development 4.3 (2016): 71-77.
- Mohir, M. I. , & Arif, K. M. (2016). Economic Analysis for Construction of Bridge for a Poverty Driven Rural Area in Kurigram District of Bangladesh. American Journal of Rural Development, 4(3), 71-77.
- Mohir, Mohirul Islam, and Kazi Mostafa Arif. "Economic Analysis for Construction of Bridge for a Poverty Driven Rural Area in Kurigram District of Bangladesh." American Journal of Rural Development 4, no. 3 (2016): 71-77.
Import into BibTeX | Import into EndNote | Import into RefMan | Import into RefWorks |
At a glance: Figures
1. Introduction
Rural transport is critical to socio-economic development and poverty reduction in Bangladesh (Planning Commission, GoB, 2016) [8]. An improved road communication system reduces road user costs and costs of production and thus facilitates socio-economic development of the country. On the other hand, Tolls will be levied on all major bridges on the National Road Network (Ministry of Communications, GoB, 2004) [6]. The country faces an enormous challenge to deliver the vision of a transport system that supports sustainable development (Ministry of Communications, GoB, 2008) [7]. Then a new approach is needed, bringing together the public and private sectors in a partnership which benefits everyone. Poverty level of Kurigram district is 63.7% (BBS, 2011) [4] and also it is a disaster prone northeastern district of Bangladesh. Most miseries in the life of the people are river erosion and this rendered a large number of people homeless, landless, asset less and also in loss of valuable belongings. There is widespread unemployment scenario in the absence of mills and factories in those districts. Only option for a large number of people is selling the manual labors mainly in the agriculture sector which is mainly limited to a single season as such labor class people have nothing to do in the other seasons when cultivation and harvesting period is over. Vast unemployment during off firm seasons brings untold sufferings and misery to the life of people of these areas by common starvation or low calorie intake far below the nutritional requirement, which is widespread known as ‘Monga’.
Among others, lack of rural transport network is the major impediment for socio-economic development of these areas. Major parts of the localities of these areas are isolated from each other by the natural barriers by the river system of Teesta, Brahmaputra and Jamuna. Gaibandah and Kurigram districts are being separated by the river Teesta. The important rural infrastructures and institutions those are vital for rural development like rural transport networks, growth centers, hat-bazar, Union Parishad Complex, health centers, educational institutions located nearby the Teesta river are being separated from each other due to barrier by the river Teesta. The construction of Teesta bridge between Sundargong Upazilla of Gaibandha district and Chilmari Upazilla of Kurigram district will establish linkage among the isolated communities, existing transport networks and other rural institutions. Besides, a new transport link will emerge in the region which will shorten the distance of travel between Kurigram district including Bhurunga mari land port with the capital city. The network needs a major bridge on the river Teesta on Panchpir Bazar-Chilmari Upazilla HQ road. There are important growth centers on both sides of the river which generate huge number of traffic across the river. The bridge is expected to improve road connectivity on a regional scale. The distance of travel from Chilmari Upazila to Dhaka would be reduced by about 160 km.
The bridge is expected to improve road connectivity on a regional scale. This type of study yet not conducted for this area. The outcomes of the study will help to make decision on impact on investment for this type of development works.
2. Objectives of the Study
The objective of the study is to know social viability and also assess economic aspects of construction of bridge for a poverty driven rural area in Bangladesh through Benefit Cost Ratio (BCR), Net Present Value (NPV) and Economic Internal Rate of Return (EIRR).
3. Literature Review
There were hardly possible to find out works on this issue due to nature of this study. However, some institutions based findings will be presented here. The basic approach to the economic analysis has been to determine the economic value of the costs and benefits over the entire life of the subprojects (ADB, 1997) [1]. Using domestic price numeraire, the financial costs of investments in infrastructure and operation and maintenance (O&M) are converted to economic costs by shadow pricing their tradable and non-tradable components, including labor, using the following assumptions: (i) shadow exchange rate factor, (ii) shadow wage rate factor of unskilled labor, (iii) shadow wage rate factor of skilled labor, and (iv) shadow price factor for other non-tradable. The cutoff point of Economic Opportunity Cost of Capital (EOCC) is usually 12 percent (ADB, 1997) [1]. A sensitivity analysis for economic analysis would be carried out for (i) a 20% increase in project cost; (ii) a 20% decrease in project benefits; and (iii) both a 20% increase in project cost estimate and a 20% decrease in project benefits (ADB, 2001) [2].
A road infrastructure project involves three types of cost in its useful life and they are construction cost, maintenance cost and road user cost (LGED, 2009) [5]. Travel Time Costs (TTC) also referred to as Values of Time are an important component of road user costs. The concept of travel time costs is based around the premise that time spent in traveling has an “opportunity cost” and could be used in an alternative activity which also produce or may produce some significant utility popularly known as benefit.
The Economic Analysis of Jamuna Bridge based on Road User Cost (RUC) Savings method found that Economic Internal Rate of Return (EIRR) of the Project is estimated at 18.2%. On the other hand, Economic Analysis of Padma Bridge found that EIRR is 20%.
4. Methodology
The fundamental concept of economic gains for construction of a bridge have been calculated based on Travel Time Cost (TTC), Vehicle Operating Cost (VOC), savings in costs associated with operation of Boat Service and capitalized value of land to be reclaimed or protected by river training works. Travel time is saved for two reasons. One is shortening of route length and another is improved of roughness. The basic concept of shortening of route length is expressed by the following figure.

The selection of the study area for this study is easy accessibility and availability of the community who have been suffered from updated communication network for a poverty driven area. Kurigram district is located in the Northwest Region of Bangladesh, covers a gross area of slightly over 2,296 sq.km and extends over 9 Upazilas with 74 Unions. The district is about 320 km from the capital city, Dhaka and is accessible by road, rail and waterways.
To evaluate social viability of the bridge, Focus Group Discussion (FGD) have been conducted for some specific indicators. The cost benefit ratio is widely used for capital expenditure decisions which is calculated by the following formula.
![]() |
![]() |
Under the NPV method, the present value (PV) of all cash inflows from the project is compared against the initial investment (I). The Net Present Value (NPV), which is the difference between the present value and the initial investment (NPV = PV-I), determines whether or not the project is an acceptable investment. Under the method, if the net present value is positive (NPV>0 or PV>I), the project should be accepted. NPV has been calculated by using the following relationship:
![]() |
Internal Rate of Return (IRR) is the rate of interest that equates the initial investment (I) with the present value (PV) of future cash inflows. That is at IRR, I = PV or NPV. Under the internal rate of return method, the decision rule is : accept the project if IRR exceeds the cost of capital; otherwise, reject the proposal. IRR is a discount rate (r) which makes NPV equal to zero (0).
![]() |
Economic analysis has been carried out in order to confirm economic viability of bridge construction. It is accepted that the project is economically feasible if the calculated IRR is higher than the Opportunity Cost of Capital (OCC) i.e. 12%., BCR is higher than 1.0 and NPV is positive. The basic approach to the economic analysis has been to determine the economic value of the costs and benefits over the entire life of the project. For the economic evaluation of this project, VOC approach is used. Road user costs (RUC) are the costs borne by the people through use of the road network facility. A road infrastructure project involves three types of cost in its useful life. They are construction cost, maintenance cost and road user cost. VOC is the physical costs of operating a vehicle such as fuel, spare parts, depression, crew costs, etc. Travel Time Costs (TTC) also referred to as Values of Time are an important component of road user costs. ACC is the physical costs of an accident measuring the value of injuries and fatalities.
In economics, opportunity cost of capital (OCC) means the next best alternative forgone. In some cases, OCC may be zero if no net-benefit accrues from the next best alternative investment, or may be even less than zero if the next best alternative project gives the negative net benefits. Shadow price (also known as accounting price) is the intrinsic or true value of a factor or product. A UN Report defines shadow price in terms of the opportunity cost of a factor or a product. The shadow price of a factor such as capital, labor or foreign exchange represents its opportunity cost or the loss to the economy that would result from a reduction in its supply by one unit. The sensitivity analysis of the possible effects of adverse changes on a project. Values of key variables are changed one at a time, or in combinations, to assess the extent to which the overall project result, measured by the economic net present value, would be affected. The Standard Conversion Factor (SCF) ratio of the economic price value of all goods in an economy at their border price equivalent values to their domestic market price value. It represents the extent to which border price equivalent values, in general, are lower than domestic market price values. The SCF will generally be less than one. Discounting factors are used to take account of the time value of money (independent of inflation). The values of the costs and benefits have to be calculated for each year of the implementation period and as well as for each year of the analysis period, which is set to be 20 years. Annual Average Daily Traffic (AADT) is the average daily traffic on a roadway link for all days of the week during a period of one year, expressed in vpd (vehicles per day). It is the total volume of vehicle traffic of a road for a year divided by 365 days.
5. Selection of Study Area
Chilmari Upazila of Kurigram District came into existence on the 15th April, 1983. The Upazila occupies an area of 225 sq.km. It is located between 25°26′ and 25°40′ north latitudes and between 89°38′ and 89°48′ east longitudes. The Upazila consists of 6 unions, 48 mouzas and 133 villages. The distribution of population of each union are given in Table 1.
According to the population census 2011 the total population of the Upazila is 1,22,841 of which 59,414 are males and 63,427 are females. The sex ratio of the Upazila is 94 males per 1000 females. In the Upazila, there are 30,966 households. It is found that in the Upazila, 91.3% of the dwelling households live in kutcha houses, 2.8% in Jhupri houses, 5.4% in semi-pucca houses and 0.60% in pucca houses. Tubewell is the dominant (96.2%) source of drinking water in the Upazila. In the Upazila, 58.3% households use sanitary latrine. Only 23.3% of the dwelling households have electricity connection. In Chilmari Upazila, 50.52% households do not have agricultural land but 67.85% of the dwelling households depend on agriculture as the main source of household income. Literacy rate for this upazila is 39.7% and poverty level for this upazila is 69% in 2005 and 61% in 2010.

6. Results and Discussions
6.1. Construction Cost and Maintenance CostThe cost of construction is spread over a period of 3 years in the following manner based on annual phasing of the projects implementation. Distribution of Cash Flows in the implementation period is given in Table 2.
Maintenance cost is spread in the analysis period based on criteria presented in the following Table 3. Routine maintenance are done every year, seal coat in every five years and overlay done in every ten years.

Besides, a new transport link will emerge in the region which will shorten the distance of travel between Chilmari and Sundarganj and also the distance will shorten with 160 km including the connection of Panchpir Bazar to Rangpur Road connection at Shiber Hat Bazar.
6.3. Vehicle Operation CostAfter bridge construction the proposed route will shorten 160 km road distance. The new route will reduce the vehicle operating cost.
6.4. Savings from Boat ServiceAccording to traffic count survey, it is found that on an average 10,000 persons are crossed the proposed bridge site each day. They pay Tk. 10 for Boat Service. Then total amount would be Tk.10 *10,000 Persons * 365 days = Tk. 365 Lakh.
All the above benefits are summarized below:
Hence the economic indicators stand as BCR is 1.91, NPV is Tk. 17645 Lakh with discount rate 15% and EIRR is 31%.
According to Project Appraisal Framework, Ministry of Planning 2005, the researchers have analyzed the following equity and efficiency indicators and found the respective results.
Total weight of the equity indicators is 5.0 and total weight of efficiency indicators is 5.0.
7. Conclusions and Recommendations
From Focus Group Discussion, it is conceived that people of the Bridge areas strongly supported construction of Bridge as they perceived that the Bridge has a positive impact on socio-economic condition by changing existing communication system through construction of the proposed bridge. It is broadly supported all classes people and stakeholders of Bridge area. There is no opposition to the proposed Bridge. All the villagers (100%) are interested to implement the Bridge project successfully. The bridge will provide significant travel time savings to the traffic in the region, particularly between Rangpur to the northwest of Bangladesh. The construction and operation of the bridge will result in significant economic benefits to the north-west region, in the form of increased production, goods and services, relocation and generation of new economic activities. Increased economic activity and consumption expenditure will lead to poverty alleviation in Rangpur region. Short-time employment generation will help the rural poor and help alleviate poverty.
Considering the level of score of the project (75.36) the project appears to be very good project. As seen in the appraisal summary table the project is very good in terms of efficiency as well as equity. Efficiency score is 41.50 while equity score is 33.86. The Project performed quite well in cost benefit analysis (BCR 1.58). It also seems to have good impact on environment creation because it is hoped to employ significant percent of local people. The project however did not have any prospect of attracting private sector investment. The reasons are primarily socio-economic. Arrangement for getting financial return would have adverse impact on the economic objectives of the project significant. On the multi-modal integration issue the project will have good impact in integration water transport network with road transport network. Currently the safety aspect of the road is very poor. If the project is implemented, the number of accidents will be significantly reduced.
References
[1] | ADB (1997), Economic Analysis Guidelines, Asian Development Bank, Manila, Philippines. | ||
![]() | |||
[2] | ADB (2001), Guidelines for Water Supply Projects, Asian Development Bank, Manila, Philippines. | ||
![]() | |||
[3] | Banglapedia (2006), Banglapedia-National Encyclopedia of Bangladesh. Asiatic Society of Bangladesh, 2006. | ||
![]() | |||
[4] | BBS (2012), Population and Housing Census 2011, Community Report, Kurigram District, Bangladesh Bureau of Statistics, Dhaka. | ||
![]() | |||
[5] | LGED (2009), Road User Cost Study for LGED Roads, Rural Infrastructure Improvement Project (RIIP), RDP-25, Local Government Engineering Department, Dhaka. | ||
![]() | |||
[6] | Ministry of Communications (2004), National Land Transport Policy, Government of the People’s Republic of Bangladesh. | ||
![]() | |||
[7] | Ministry of Communications (2008), Integrated Multi-Modal Transport Policy, Government of the People’s Republic of Bangladesh. | ||
![]() | |||
[8] | Planning Commission (2016), Seventh Five Year Plan, Ministry of Planning, Government of the People’s Republic of Bangladesh. | ||
![]() | |||
[9] | Project Appraisal Framework (2005), Transport Sector Coordination Wing, Planning Commission, Government of the People’s Republic of Bangladesh. | ||
![]() | |||